Skip to main content

Voting System Testing Update – May 4, 2020

Voting Systems Testing Updates
374x280testingsystemsupdate.jpg

This blog is an effort to keep everyone informed of the progress of voting systems that are in the EAC’s Testing and Certification Program.

 

MicroVote 4.4: Project Manager – Paul Aumayr; VSTL – Pro V&V

The application was received on Thursday, October 31st, 2019 and the test plan was approved on January 24, 2020.  Initial Decision was made on April 20, 2020

Certification Initial Phase - Microvote 4.4 as of May 1, 2020

 

Dominion Democracy Suite 5.5-C: Project Manager – Paul Aumayr; VSTL – Pro V&V

The application was approved on March 19, 2020 and the test plan was approved on April 17, 2020

Testing phase for Dominion Democracy 5.5 as of May 4, 2020

 

If you would like more information about the certification process, please read Chapter 4 and 5 of the Testing and Certification Program Manual. Please contact Jerome Lovato ([email protected]) for additional information about a particular voting system.

Keywords
voting systems under test, certified voting systems, test and cert blog