Voting System Testing Update 2.28.17

Feb 28, 2017

The “Voting System Testing Update” blog is an effort to keep everyone informed of the progress systems in the EAC’s Testing and Certification Program are making each week.  We hope that this adds additional transparency to our process and allows stakeholders to get a weekly update about test campaigns that impact their jurisdiction.

Voting Systems under Test:

ClearBallot Group ClearVote 1.4. Pro V&V and ClearBallot are working on revisions to the Test Plan based on EAC comments. If you would like to view documents related to this test campaign, please visit our website. Brian Hancock is the project manager on this test campaign

ESS EVS 5.2.2.0. EAC certified this system on February 27th. If you would like to view documents related to this test campaign, please visit our website. Ryan Macias is the project manager on this test campaign.

ESS EVS 5.4.0.0. EAC certified this system on February 24th. If you would like to view documents related to this test campaign, please visit our website. Jessica Myers is the project manager on this test campaign.

Everyone Counts elect Quad Audit 4.4.0. EAC provided comments on the Test Plan to Pro V&V on January 11th. Pro V&V is working on revisions to the Test Plan. If you would like to view documents related to this test campaign, please visit our website. Ryan Macias is the project manager on this test campaign.

Hart Verity Voting 2.2.1. EAC approved the Test Plan on February 23rd and received the draft Test Report on February 24th. EAC will provide comments or approval to SLI by March 3rd. If you would like to view documents related to this test campaign, please visit our website. Jessica Myers is the project manager on this test campaign.

Microvote EMS 4.2. Pro V&V is working through the Test Plan for this project. If you would like to view documents related to this test campaign, please visit our website. Brian Hancock is the project manager on this test campaign.

Unisyn OpenElect 1.3.0.2. EAC received the Test Report on February 21st. If you would like to view documents related to this test campaign, please visit our website. Brian Hancock is the project manager on this test campaign.

Unisyn OpenElect 2.0. EAC, Pro V&V and Unisyn are discussing plans for testing this system. If you would like to view documents related to this test campaign, please visit our website. Brian Hancock is the project manager on this test campaign.

If you would like more information about the certification process, please read Chapter 4 and 5 of the Testing and Certification Program Manual.

 

 